Project Summary

This summer, the Village of Oregon and Speedway Sand and Gravel will complete a reconstruction of the Janesville St/Perry Pkwy intersection. The project will include pavement replacement, new concrete curb and gutter, new sidewalks, and the addition of a new traffic signal. 

 

Project Schedule

Construction will begin July 25, 2022 (Monday) and will last approximately 30 days. The scheduled last day of construction is August 19, 2022.

 

Traffic Control

Perry Pkwy will be closed at Janesville St from both the north AND south for the duration of the project. Janesville St will remain open with flaggers, but residents should expect periods of delays at the intersection during construction.

INFORMATION AVAILABLE HERE https://www.vil.oregon.wi.us/pw_janesvilleperryint